New Server Room
From FreekiWiki
Here's a timeline of major events in the new server room.
- Februrary, 2005
- String temporary cables over the top of the "rafters" to the first column of shelves.
- Move current servers temporarily onto the first column of shelves.
- March, 2005
- Bolt down overhead ladder (Nathan)
- Place and bolt down hub / switch / patch panel racks (Nathan)
- Bolt down shelving / Move servers to permanent location on shelves (Nathan)
- Move server rack into place
- Build permanent cables
- Move servers from old server room (and elsewhere) into new server room
(NOTE: Current servers means the servers that are already in the new server room, as opposed to those in the old server room or elsewhere at Free Geek.)
(There is an RT queue that tracks this project.)