Difference between revisions of "Specific Options for Reducing Staffing Costs"

From FreekiWiki
Jump to navigation Jump to search
m
Line 2: Line 2:
  
 
As we review everything, we need to spell out what specific measures we could take. We'll need to estimate the financial costs and savings of each, the other costs (staffing shortages, impact on programs, etc.), and the problems associated with each option.
 
As we review everything, we need to spell out what specific measures we could take. We'll need to estimate the financial costs and savings of each, the other costs (staffing shortages, impact on programs, etc.), and the problems associated with each option.
 +
 +
Target #1 = $2,700.
 +
 +
Target #2 = $5,400 (including target #1).
 +
 +
 +
== Across the board wage cut ==
 +
A 5% wage cut would save us $1,162.58. 23,250 / month on non health care benefits.

Revision as of 14:39, 1 March 2005

This is part of the Reduction Committee Tasks.

As we review everything, we need to spell out what specific measures we could take. We'll need to estimate the financial costs and savings of each, the other costs (staffing shortages, impact on programs, etc.), and the problems associated with each option.

Target #1 = $2,700.

Target #2 = $5,400 (including target #1).


Across the board wage cut

A 5% wage cut would save us $1,162.58. 23,250 / month on non health care benefits.