Difference between revisions of "Space Usage Projects"
Jump to navigation
Jump to search
(created page for managing Space Usage projects) |
("clear path to rear bathrooms" project) |
||
| Line 1: | Line 1: | ||
| − | = | + | == Clear Path to Rear Bathrooms == |
| + | The path to the restrooms behind the Laptops area needs to be fully cleared and handicap-accessible before Geek Fair on August 23rd. | ||
| + | === Dependencies === | ||
| + | * Organizing the Facilities Maintenance area | ||
| + | === Committees & Individuals to Include in Discussion === | ||
| + | * Action | ||
| + | === Next Steps === | ||
| + | * discuss at Space Cadets meeting 7/8/08 | ||
| + | |||
| + | |||
| + | |||
| + | |||
== Name of Project == | == Name of Project == | ||
* Description of project | * Description of project | ||
| Line 6: | Line 17: | ||
=== Next Steps === | === Next Steps === | ||
* include individual commitments, progress with these commitments, and a timeline for checking-in | * include individual commitments, progress with these commitments, and a timeline for checking-in | ||
| − | |||
| − | |||
| − | |||
= EXAMPLE PROJECT = | = EXAMPLE PROJECT = | ||
Revision as of 17:25, 3 July 2008
Clear Path to Rear Bathrooms
The path to the restrooms behind the Laptops area needs to be fully cleared and handicap-accessible before Geek Fair on August 23rd.
Dependencies
- Organizing the Facilities Maintenance area
Committees & Individuals to Include in Discussion
- Action
Next Steps
- discuss at Space Cadets meeting 7/8/08
Name of Project
- Description of project
Dependencies
Committees & Individuals to Include in Discussion
Next Steps
- include individual commitments, progress with these commitments, and a timeline for checking-in
EXAMPLE PROJECT
Cafeteria Al Fresco
- This project will move the cafeteria to the roof. By moving the cafeteria to the roof volunteers will have access to sunshine and fresh air as well as a relaxing place to take a break.
Dependencies
- get Council approval
- update budget for third quarter
- Building a shelter on the roof to accommodate volunteers during the rainy season
- Designing and constructing an elevator that goes from the ground floor up to the roof
- acquiring materials
- who will build it?
Committees & Individuals to Include in Discussion
- Inreach deals with Volunteer Rewards
- Action deals with the physical building
- landlord
- other tenants
Next Steps
- Moving the tables & chairs to the roof
- Sally will do this as soon as the elevator is constructed. She will poke elevator builder.
- Getting the refrigerator up to the roof
- George will do this as soon as the elevator is constructed.
- Get an enormous flat-panel TV so volunteers can watch FOX news during their break
- John will ask friend about where to get this. He will do this by 5/30/08.
- Note from John - I've asked my friend and he's looking around and will get back to me next week.