Difference between revisions of "Free Geek Gresham"

From FreekiWiki
Jump to navigation Jump to search
m
 
(6 intermediate revisions by 3 users not shown)
Line 27: Line 27:
 
== Proposal Outline ==
 
== Proposal Outline ==
  
* Start in temporary location at the Gresham Ford site a soon a feasible (Continue search for appropriate space).
+
'''Preliminary'''
* Send 1 FG-PDX staffer to run new location for approx. three months.
+
 
 +
* Create FG Gresham Community Council, start having regular meetings in Gresham.
 +
* Contact local non-profits, seeking council participation.
 +
* Search for appropriate space (ongoing).
 +
 
 +
'''After space is a acquired:'''
 +
 
 +
* Send 1 FG-PDX staffer to coordinate new location for approx. three months.
 
* Start allowing community members to volunteer, create community council.
 
* Start allowing community members to volunteer, create community council.
 
* Start accepting donations on a limited basis.
 
* Start accepting donations on a limited basis.
 
* Start recycling operation ASAP.
 
* Start recycling operation ASAP.
 
* Hire additional staff as revenue increases.
 
* Hire additional staff as revenue increases.
* Replace FG-PDX staff with permanent FG-Gresham staff as needed/possible.
+
* Replace FG-PDX staff with permanent FG-Gresham staff as needed.
  
 
== Project Needs ==
 
== Project Needs ==
  
* $5,000 - $6,000 in startup funds, enough to pay for utilites, insurance and one staff person for two months.
+
* $10,000 - $15,000 in startup funds (possibly more due to high rent costs)
* $5,000 - $10,000 in follow up funds to expand staff and other income generating operations, begin paying rent.
+
* $10,000 - $15,000 in follow up funds to expand staff and other income generating operations.
 
* $10,000 in additional funds to make up operational loss until DEQ grant funds are available in the beginning of 2007.
 
* $10,000 in additional funds to make up operational loss until DEQ grant funds are available in the beginning of 2007.
 
* Vehicle for transportation of personnel and materials between FG-PDX and FG-Gresham.
 
* Vehicle for transportation of personnel and materials between FG-PDX and FG-Gresham.
Line 45: Line 52:
 
* Furniture
 
* Furniture
 
* Construction materials
 
* Construction materials
 +
 +
== Organizational Structure Proposal ==
 +
 +
* Undecided at this point.
  
 
== Presentations ==
 
== Presentations ==
Line 52: Line 63:
 
* 03/23 - Gresham Area Chamber of Commerce
 
* 03/23 - Gresham Area Chamber of Commerce
 
* 04/05 - Gresham ESCAC (Environmental Services Community Advisory Committee).
 
* 04/05 - Gresham ESCAC (Environmental Services Community Advisory Committee).
 +
 +
[[Category:Free Geek Intergalactic]]
 +
[[Category: Space Use]]

Latest revision as of 18:08, 16 June 2009

Overview

The community of Gresham is interested in having a Free Geek computer reuse and recycling operation in their area. The thought for now is to run this as a branch of Free Geek Portland rather than starting a seperate non-profit.

Community Partners

  • City of Gresham - Department of Environmental Services
  • Gresham Area Chamber of Commerce
  • Gresham Optimists Club
  • Gresham Ford

Resources

These are offers that have been made, none accepted to date.

Short Term

  • 7,000 SF temporary facility (defunct Suzuki dealership), 2 months free rent, then slidng scale (pay what we can) for up to one year - donated by Gresham Ford
  • Office furniture - donated by the City of Gresham, desks, chairs and filing cabinets.
  • Vehicle - 1990 Isuzu Trooper, 4 cylinder - donated by David Pool

Long Term

  • Garbage fee rate increase through the City of Gresham, could result in $5,000 to $25,000 per year.
  • DEQ Solid Waste and Recycling grant, approx. $50,000 available in Jan. 2007 (application due Sept '06).

Proposal Outline

Preliminary

  • Create FG Gresham Community Council, start having regular meetings in Gresham.
  • Contact local non-profits, seeking council participation.
  • Search for appropriate space (ongoing).

After space is a acquired:

  • Send 1 FG-PDX staffer to coordinate new location for approx. three months.
  • Start allowing community members to volunteer, create community council.
  • Start accepting donations on a limited basis.
  • Start recycling operation ASAP.
  • Hire additional staff as revenue increases.
  • Replace FG-PDX staff with permanent FG-Gresham staff as needed.

Project Needs

  • $10,000 - $15,000 in startup funds (possibly more due to high rent costs)
  • $10,000 - $15,000 in follow up funds to expand staff and other income generating operations.
  • $10,000 in additional funds to make up operational loss until DEQ grant funds are available in the beginning of 2007.
  • Vehicle for transportation of personnel and materials between FG-PDX and FG-Gresham.
  • Forklift
  • Shelving
  • Furniture
  • Construction materials

Organizational Structure Proposal

  • Undecided at this point.

Presentations

  • 02/22 - City of Gresham - DES
  • 03/01 - Gresham Ford (at Gresham City Hall)
  • 03/23 - Gresham Area Chamber of Commerce
  • 04/05 - Gresham ESCAC (Environmental Services Community Advisory Committee).